You are here

Project Information and Updates

Major Projects in Construction:

Projects in Progress

 

Housing Expansion Phase 1 – Parkside North Housing

Summary:   The new Parkside North Housing project is the first phase of the Housing Expansion project.  The proposed residential facility will be a 124,892 GSF 3 and 4-story building which will provide an additional 476 beds to the current CSULB student housing program.  In addition to student dorm rooms the building will offer pod study rooms, kitchens, multiple levels of community space and distinctive outdoor courtyard space.  The new housing project is to be a “home away from home” experience that is not just meant to be a place to live but a way of life.  The project is to set a new standard for CSU and higher education as well as provide a model for future high performance buildings that aim towards the CSU’s carbon neutrality 2030 goals.  The Parkside North Housing building design aims to reach the most progressive and regenerative sustainability goals which will contribute to this project as being the first Net-Zero Energy, Living Building Challenge Petal Certified, and LEED Platinum residential building in the CSU system. ​

  • Project Construction Cost:              $70 million
  • Construction Start Date:                 August 2019
  • Construction Completion Date:      May 2021
  • Project Delivery Method:                Collaborative Design-Build
  • Architect:                                         Gensler
  • Design-Builder:                               McCarthy Building Co.
  • University Design and Construction Team:               
    • Martin Grant, Program Manager, Capital Construction
    • Monica Amalfitano, Associate Director/Campus Engineer
    • Lisa Salgado, Construction Project Manager
    • Karin Montgomery, Project Engineer
    • Tom Sanchez, Inspector of Record

Render of the front of the new Parkside North Housing

Render of the Interior Courtyard of the new Parkside North Housing

 

 

Psychology Curtain Wall Replacement

Summary:   This project is replacing the aging Curtain Wall system at the Psychology building. The replacement Curtain Wall will preserve the historic aesthetics of the Psychology building. Pedestrian and vehicular traffic will be slightly affected but access will be maintained. Signage will be posted to direct pedestrian traffic and alternate accessible routes will be available.

  • Project Cost (Construction GMP): $4,961,679
  • Construction Start Date: July 2, 2019
  • Construction Completion Date: March 20, 2020
  • Project Delivery Method: Collaborative Design-Build
  • Architect: DLR Group
  • Design-Builder: Swinerton Builders
  • University Design and Construction Team:
    • Jason Chao, Project Manager
    • Rafael Quezon, Construction Manager
    • Chris Peterson,  Project Engineer
    • Ed Puga,  Inspector of Record
    • Roberto Rodriguez-Garzon, Student Intern

Render of end result of replacing the aging Curtain Wall on the Psychology Building

 

 

Microbiology HVAC

Summary:  This project consists of replacing the existing HVAC system in the Microbiology building.  The existing fan coil units that are located along the external walkways are beyond their lifetime and no longer energy efficient.  The units at each level will be replaced with new units.  The heating and chilled water piping will also be replaced.  Other improvements include painting the building exterior walls and handrails and replacing the exterior fascia.

  • Project Cost:  $9,099,000 million overall project cost
  • Construction Start Date:  September 20, 2019
  • Construction Completion Date: July 20, 2020
  • Project Delivery Method:  Collaborative Design - Build
  • Architect: DLR Group
  • Design-Builder:  Swinerton Builders
  • University Design and Construction Team:
    • Stephanie Gutierrez, Project Manager
    • Rafael Quezon, Construction Manager
    • Chris Peterson, Project Engineer
    • Dana Morley, Project Engineer
    • Danny Blakely, Inspector of Record

 

 

Brotman Hall Suite 123 Enrollment Services Phase 3

Summary:   Suite 123 will undergo a complete renovation.  The area will still be used for office space, but it will be gutted in order to accommodate a new space efficient layout that consists of some private offices, many open work stations, two huddle areas, two conference rooms, and a  break room. The lighting fixtures and mechanical ductwork will be replaced to accommodate the new layout of the space, and there will be all new interior finishes, including office furniture.

  • Project Cost:  $5,179,880 overall project cost
  • Construction Start Date:  October 1, 2019
  • Construction Completion Date: April 30, 2020
  • Project Delivery Method:  Construction Manager at Risk (CMAR)
  • Architect: Cuningham Group
  • Construction Manager at Risk:  Swinerton Builders
  • University Design and Construction Team:
    • Stephanie Gutierrez, Project Manager
    • Marie-Jeanne Ayoub, Construction Manager
    • Dana Morley, Project Engineer
    • Tammy Hinds, Inspector of Record

Brotman Hall  Room 123 for Enrollment Services Rendering

Brotman Hall  Room 123 for Enrollment Services Rendering