Up and Coming Projects

Alumni Center 

CSULB Alumni Center

The Alumni building will serve as a welcoming campus portal that inspires, facilitates and sustains alumni interaction by providing a one-of-a kind special event and gathering space for the Campus and Community. It will be the symbolic home for all Alumni returning to Campus showcasing 49er memorabilia and providing a welcoming space to socialize and continue the friendships formed at the University. It will bring students and alumni together in a single location to promote career development, networking, mentoring and opportunities. It will be an inspired venue for learning, engagement and entrepreneurial activities.

  • Total Project Cost : $11,500,000 Estimate
  • Construction Start Date: November 2020 Estimate
  • Construction Completion February 2022 Estimate
  • Project Delivery Method: Construction Manager at Risk (CMAR)
  • Architect: John Friedman Alice Kimm Architects
  • Construction Manager at Risk: The PENTA Building Group
  • University Design and Construction Team:
    • Jason Chao, Project Manager
    • Marie-Jeanne Ayoub,  Construction Manager
    • Chris Peterson, Project Engineer
    • Ed Puga, Inspector of Record

Los Alamitos / Los Cerritos Renovation

Los Cerritos and Los Alamitos Lounge

The Los Alamitos and Los Cerritos Renovation project consists of performing a comprehensive renovation of these two buildings which were built in 1959. Some of the finishes and part of the infrastructure in these buildings are original and need to be updated. The preliminary project scope for the project includes new finishes throughout (except for select areas that were recently renovated), mechanical and electrical upgrades, installation of a modular elevator at Los Alamitos to improve ADA access to the building, roof replacement at Los Alamitos, one new students kitchen at each building, installation of a fire suppression system (sprinklers) and a new fire alarm system. This project will bring the Los Alamitos and Los Cerritos buildings up to date, significantly improving the experience of the students and staff that use and maintain the facilities.  

  • Total Project Cost: $38,000,000 Estimate 
  • Construction Start Date: December 2020 Estimate
  • Construction Completion Date: Agust 2021 Estimate 
  • Project Delivery Method: Construction Manager at Risk (CMAR)
  • Architect: Gensler
  • Contractor: Swinerton
  • University Design and Construction Team:
    • Sandra Vigo, Project Manager

Heating Hot Water Replacement Phase 3

This underground piping replacement project will repair our failing underground heating hot water distribution on the south campus lateral connections to the buildings and also the north campus loop near KIN, Engineering, and the Design buildings.

  • Total Project Cost: $11,800,000
  • Construction Start Date: Summer 2021 Estimate
  • Construction Completion Date: Spring 2023
  • Project Delivery Method: TBD
  • Architect: TBD
  • Contractor: TBD
  • University Design and Construction Team:
    • Monica Amalfitano, Project Manager

FCS Child Care Project

The project will include renovation and new construction to upgrade and expand the child care and teaching facilities for the College of Health and Human Services (CHHS) to allow for the growth of the Child and Family program on campus.  The project will yield a significant increase in the quantity and range of childcare services available for children of students attending college as well as increase the number of graduates whose training will, in turn, allow them to improve the quality and availability of childcare programs throughout California.

  • Total Project Cost: $12,000,000
  • Construction Start Date: TBD
  • Construction Completion Date: TBD
  • Project Deliver Method: Construction Manager at Risk (CMAR)
  • Architect: TBD
  • Construction Manager at Risk: TBD
  • University Design and Construction Team:
    • Jason Chao,  Project Manager
    • TBD,  Construction Manager
    • TBD,  Project Engineer
    • TBD,  Inspector of Record

PH-1, FO4, FO5 Replacement Project

The project will construct a new 83,500 ASF/128,500 GSF building for the College of Health and Human Services (CHHS) to replace the existing Peterson Hall 1 building (PH1) (#37) and the Faculty Office 4 (FO4) (#36) and Faculty Office 5 (FO5) (#45) temporary office buildings. This project seeks to consolidate the College of Health and Human Services from multiple locations across campus to allow efficient operation and enable the University to increase its contribution to improving the quality and availability of healthcare professionals in California.

This project seeks to consolidate the College of Health and Human Services from multiple locations across campus to improve efficiency and allow for effective collaboration and sharing of college resources.  It will arrange the college around four functional frames to maximize utilization of shared space and technology resources.  The building design will create a collaborative culture among CHHS faculty, staff, students and its community outreach clinics.  The new teaching spaces and clinics will prepare students for the workforce by providing them with state of the art equipment and techniques utilized in the industry today. The new building will include faculty space, student collaboration space, teaching labs, research labs, administration space, a medical simulation center, and a clinic to be operated in corporation with a local regional hospital.

  • Total Project Cost: $149,600,000
  • Construction Start Date: March 2023 Estimate
  • Construction Completion Date: March 2025 Estimate
  • Project Deliver Method: Construction Manager at Risk (CMAR)
  • Architect: TBD
  • Construction Manager at Risk: TBD
  • University Design and Construction Team:
    • Jason Chao,  Project Manager
    • TBD,  Construction Manager
    • TBD,  Project Engineer
    • TBD,  Inspector of Record

UMC Renovation

The University Music Center (UMC) is home to the Bob Cole Conservatory of Music, a prestigious music program with the mission “To educate and inspire exceptional students for successful careers as artists, teachers, and scholars through practical global experiences in a vibrant performance-oriented setting.”

New Building

The Project will include a new building (approximately 10,000 to 12,000 gross square feet in size) designed to house music lesson rooms, practice rooms, and student common areas.  The new building program will replace the existing 61 practice rooms that are currently used for instrument and vocal practice and which will be demolished.  The new building could be located on open space to the west side of the existing UMC complex, but further studying is required. 

Outdoor Student Hub

The Project will include an outdoor student hub for students to study, practice, and collaborate throughout the day and night.  The outdoor space will include a new vertical façade that is intended to hide the back of house elements that will be exposed once the 61 practice rooms are demolished.  The outdoor design will include student seating, study space, practice space, and  vending area, as students are known to practice and collaborate all hours of the day and night.

Daniel Recital Hall

The Daniel Recital Hall is an important venue where students showcase their talents to their professors, their family, and the CSULB community.  It is in need of major improvements, such as aesthetics, acoustics, and accessibility upgrades. The design will include a remodel of the ticket booth, main entrances and exits, main audience area and other support spaces, with special attention to accessibility.  New seating, flooring, painting, and acoustical treatments are intended to give this space a modern look. 

Overall Landscape, outdoor WiFi, along with ADA upgrades will be completed as part of this project.

  • Total Project Cost: $24,000,000
  • Construction Start Date: November 2021
  • Construction Completion Date: January 2023
  • Project Deliver Method: Construction Manager at Risk (CMAR)
  • Architect: TBD
  • Construction Manager at Risk: TBD
  • University Design and Construction Team:
    • Stephanie Gutierrez,  Project Manager
    • TBD,  Construction Manager
    • TBD,  Project Engineer
    • TBD,  Inspector of Record