HRL Fire Alarm Upgrade

This project will upgrade the current fire alarm system for Parkside, Hillside and International House from Simplex to Notifier.  This will include a “like for like” replacement of fire alarm devices along with adding additional speaker strobes in accordance with NFPA 70 and NFPA 72, 2019 Edition with CA Amendments. The existing fire alarm panel will be relocated to a new closet as the existing location does not meet code clearances.  New multimode fiber will be installed from MDFC to the new Notifier panels. New fire alarm graphics for the housing fire alarm project will be added to the existing Notifier Stations at the Campus Police Department and FM Fire Shop.

  • Total Project Cost: $8,000,000
  • Construction Start Date: May 2023
  • Construction Completion Date: August 2023
  • Project Delivery Method: Construction Manager at Risk (CM@R)
  • Architect: MMA
  • Construction Manager at Risk: 2H Construction
  • University Design and Construction Team:
    • Marc Joves,  Project Manager
    • Taylor Gibbons, Construction Manager
    • Lelyn Scurlark,  Project Engineer
    • Ed Puga, Inspector of Record