UTC and TA 033 Renovation

Interior alteration of both the 1st and 2nd floor of the UTC building, as well as the renovation of TA-033 and ADA upgrades to the adjacent restrooms. This includes a film equipment center, audio suite, and faculty offices for the Film Department. 

  • Total Project Cost: $7.1 Million
  • Construction Start Date:  June 5, 2023
  • Construction Completion Date: January 18, 2024
  • Project Delivery Method: Construction Manager at Risk 
  • Architect: AC Martin
  • Construction Manager: 2H Construction
  • University Design and Construction Team:
    • Ben Wilson  Project Manager
    • Vivek Ghimire, Construction Manager
    • Ben Wilson, Project Engineer
    • Danny Blakley, Inspector of Record