You are here

Project Information and Updates

Construction Impacts:

Heating Hot Water Infrastructure Project

October 3, 2018 – December 4, 2018

On October 3rd, 2018, the Infrastructure Heating Hot Water project contractor will be starting pipe placement operations along East Campus Drive and will continue to work across the upper campus. Intermittent traffic delays between 7:00 a.m. and 3:30 p.m. will occur during material transportation and as the construction progresses near MLSC, FO4 and UTC buildings. One lane will be open at all times at East Campus Drive with flaggers directing traffic in both directions, and both lanes will be open after hours. Construction along East Campus Drive is expected to complete by December 4th, 2018.

Construction operations at the remainder of the work segments will follow the timeline indicated on the project map and will be coordinated further with the pertinent facilities and parties as the work progresses. Signage will be posted to warn and assist the vehicular and pedestrian traffic, and fencing will be erected where needed. For questions, please contact PPFM Customer Service at (562) 985-HELP (4357) or email PPFM-CustomerService@csulb.edu.

 

Major Projects in Construction

Projects in Progress

Peterson Hall #2 Renovation Project- Student Success Center

Summary: The Peterson Hall 2 Renovation Project will provide a “Student Success Center”, a consolidated home for multiple campus organizations that primarily help disadvantaged and struggling students stay in school and attain their degrees. The renovation project will also provide new academic labs and studio spaces for various programs. An existing open exterior area on the south side of the building will be turned into a thriving outdoor plaza with abundant seating and Wi-Fi. The building will also have a new student lounge that will be built at the second floor that will maximize views towards the adjacent quad. All major systems of the building will be replaced in the renovation but the shell of the building will be maintained to reduce waste.  This renovation will achieve US Green Building Counsel’s prestigious LEED Gold certification for its sustainable design elements.

Construction Progress Reports Available via Email

Design and Construction Services (DCS) introduced a new email bulletin to communicate the progress of the Student Success Center Project to the campus and neighboring communities. This email bulletin will be sent only to campus members that subscribe to this correspondence. It is meant to keep interested individuals informed of the pertinent activities on the PH2 construction site that could have an effect on immediate areas outside of the project boundary.

Examples of items that may be communicated weekly are:

  • Current construction schedule
  • Upcoming construction activities that may affect adjacent buildings
  • Scheduled major deliveries
  • Weekend, night or holiday work
  • Parking closures
  • Any other planned activities that could possibly affect the campus community
  • Explanation of recent unforeseen or unplanned activities that caused an impact

An email will be sent once a week, scheduled for Fridays. The first email correspondence is scheduled for Friday, December 1, 2017. If you would like to subscribe to this weekly progress email, please email Jeff.Bahr@csulb.edu with your request. Please note that DCS will continue to send campus wide emails reporting all major activities that will affect the campus at large. If you are only concerned with major activities, there is no need to subscribe to receive these more detailed progress updates.

Email updates will also be posted on the Design and Construction website under “Project Information and Updates.”

CSULB wants to be a good neighbor as we build our future Student Success Center. If you have questions or comments please feel free to contact the onsite Construction Manager Jeff Bahr at Jeff.Bahr@csulb.edu or (951) 970-6354. Our goal is to minimize surprises and disruptions as much as possible and make this experience positive for everyone.

Project Update, November 16, 2018

The following events are scheduled to take place next week, November 17th through November 23rd, CSULB PH2 Renovation Project:

Upcoming Construction Activities that may affect adjacent buildings next to the PH2 Building

The following activities will take place next week and will cause noise. These activities will not be a constant noise, the noise will be at random short intervals and is not anticipated to be at a level that would be disruptive.

  • Continued Interior construction for finishing walls (Wood slat finishes and mud at basement, 1st and 2nd Floors) and walls at the west student lounge, finish work for electrical and Heating, Cooling and Ventilation (HVAC) systems, painting and ceiling grid tile installation for the PH2 Building will continue throughout next week. At areas where rough-in is done, the contractor is continuing installation of floor finishes of carpet and rubber flooring. Work for the central stairs also ongoing for next week for paint and handrails at the central stairs.  Work also ongoing for the elevator assembly (install of car and floor door assemblies). Interior glass installation at offices and test centers on going. The noise level from this operation is anticipated to be low. Small tools will be in use.
  • Parking Lot E7 work is ongoing through November 23rd, 2018. The work being planned for relocation of the parking lot ticket pay station.  The majority of the parking lot is available during this construction period with the exception of the south aisle (for continued laydown) and the two accessible spaces near the existing ticket pay station. Access to buildings PH1, Microbiology and F0 5 will still be limited in impacted by this work, and signage is in place by the contractor directing pedestrian traffic where to access buildings. Some parking stalls may be temporarily unusable when the contractor stages and pours the concrete for pads on the east side of PH2, Monday November 5th.

The following activities will take place next week and will cause noise. We have added sound insulation around the jackhammering to lessen the noise that will be produced outside the building. We will keep a diligent watch on the noise that is emitted in order to keep it under Campus regulations.

  • Wood slats/benches, utility finishes and data cable pulls continuing this week. Additionally framing for the exterior doors at the east stairwell ongoing. This work when performed will be intermittent. The noise to expect will be from continued saw-cutting metal studs, tiles and pipes, compressor running (in basement) and shop vacuums. This is work that must occur and with the method to be used. Should the work be too disruptive, we may need to move to the weekends to be completed.
  • Site work with for the central court rebar and forms, concrete stairs at the Southwest side of the project is continuing through this coming week. South side canopy welding ongoing through next week. Storm drain work at the north side walkways and at the east end of the building on hold until completion of landscaping irrigation system. North door ramp and stairs ongoing through next week. The use of a backhoe to dig and re-compact the soil for the trenches will be ongoing for this work. Noise levels will be monitored to minimize disturbance to the University.
  • Swinerton has begun working a swing shift at night between 3 pm and 11 pm.  Work will be flooring repair and finish treatment (grinding and buffing).

This next week all deliveries to the central quad will be scheduled between the hours of 7:00 A.M. and 9:00 A.M.

There will be work this weekend.

  • Contractor will be working this weekend of November 17th – Swinerton will have partial crews for electricians/data, draperies, painting, elevator and rough cleaning at the interior of the building. Swinerton will also be welding at the south exterior canopy. 

The project has experienced a minor delay in completing the central stair and the installation of the fire rated walls at the utility shafts, however the contractor is still currently working on a schedule mitigation in order to open as planned in January of 2019.

Please email or contact me at (562) 825-8698 for any questions or comments.

Project Update, November 9, 2018

The following events are scheduled to take place next week, November 10th through November 16th, CSULB PH2 Renovation Project:

Upcoming Construction Activities that may affect adjacent buildings next to the PH2 Building

The following activities will take place next week and will cause noise. These activities will not be a constant noise, the noise will be at random short intervals and is not anticipated to be at a level that would be disruptive.

  • Continued Interior construction for finishing walls (Wood slat finishes and mud at basement, 1st and 2nd Floors) and walls at the west student lounge, finish work for electrical and Heating, Cooling and Ventilation (HVAC) systems, painting and ceiling grid tile installation for the PH2 Building will continue throughout next week. At areas where rough-in is done, the contractor is continuing installation of floor finishes of carpet and rubber flooring. Work for the central stairs also ongoing for next week for paint and handrails at the central stairs.  Work also ongoing for the elevator assembly (install of plates and rails of elevator shaft and rough in electrical). Interior glass installation at offices and test centers on going. The noise level from this operation is anticipated to be low. Small tools will be in use.
  • Parking Lot E7 work is ongoing through November 16th, 2018. The work being planned for relocation of the parking lot ticket pay station.  The majority of the parking lot is available during this construction period with the exception of the south aisle (for continued laydown) and the two accessible spaces near the existing ticket pay station. Access to buildings PH1, Microbiology and F0 5 will still be limited in impacted by this work, and signage is in place by the contractor directing pedestrian traffic where to access buildings. Some parking stalls may be temporarily unusable when the contractor stages and pours the concrete for pads on the east side of PH2, Monday November 5th.

The following activities will take place next week and will cause noise. We have added sound insulation around the jackhammering to lessen the noise that will be produced outside the building. We will keep a diligent watch on the noise that is emitted in order to keep it under Campus regulations.

  • Wall tile and grout installation on the first and basement floor restrooms, wood slats/benches, utility finishes and data cable pulls continuing this week. This work when performed will be intermittent. The noise to expect will be from continued saw-cutting metal studs, tiles and pipes, compressor running (in basement) and shop vacuums. This is work that must occur and with the method to be used. Should the work be too disruptive, we may need to move to the weekends to be completed.
  • Site work with for the central court rebar and forms, concrete sitting walls at the Southwest side of the project is continuing through this coming week. South side canopy welding ongoing through next week. Storm drain work at the north side walkways and at the east end of the building on hold until completion of landscaping irrigation system. The use of a backhoe to dig and re-compact the soil for the trenches will be ongoing for this work. Noise levels will be monitored to minimize disturbance to the University.

This next week all deliveries to the central quad will be scheduled between the hours of 7:00 A.M. and 9:00 A.M.

There will be work this weekend.

  • Contractor will be working this weekend of November 10th – Swinerton will have partial crews for electricians/data at the interior of the building. On November 11th Swinerton plans to have 2 elevator installers working on site.

The project has experienced a minor delay in completing the central stair and the installation of the fire rated walls at the utility shafts, however the contractor is still currently working on a schedule mitigation in order to open as planned in January of 2019.

Please email or contact me at (562) 825-8698 for any questions or comments.

Peterson Hall Project Update (PPT). This describes the project staging area, logistic plans, Faculty and Staff Q&A and more.

  • Project Cost: $44,963,984.00
  • Construction Start Date: September 23, 2017
  • Construction Completion Date: December 16, 2018
  • Project Delivery Method: Construction Manager at Risk
  • Architect: Smith Group JJR
  • Construction Manager at Risk (Contractor): Swinerton Builders
  • University Design and Construction Team:
    • Mark Zakhour- Director, Construction Services
    • Jeff Bahr - Construction Manager
    • Joon Kang- Project Engineer
    • Ben Wilson- Project Engineer
    • Ed Puga- Inspector of Record

<p>This frameset document contains:</p> <ul><li><a href="//www.youtube.com/embed/4JtPeSGOvA8?modestbranding=0&amp;html5=1&amp;rel=0&amp;autoplay=0&amp;wmode=opaque&amp;loop=0&amp;controls=1&amp;autohide=0&amp;showinfo=0&amp;theme=dark&amp;color=red&amp;enablejsapi=0">Video Link-"Animated Walkthrough of New Student Success Center"</a></li> </ul>

Peterson Hall Renovation

 

 

College of Continuing and Professional Education- CCPE New Classroom Project

Summary: The College of Continuing and Professional Education at Cal State Long Beach (CCPE) has evolved to an internationally recognized program, attracting students from as far as Dubai and Central China, as well as serving the educational needs of adult learners in the community and on the campus itself.   Currently, CCPE holds classes in the University Foundation building and various facilities on and off campus. This new building would centralize and consolidate these spaces.

The proposed facility will be a 34,000 sf, 3-story building which will house classrooms, student interaction spaces, and a multi-purpose conference facility. The conference area of the facility includes an outdoor pre-function space that leads into an interior conference room with a capacity of approximately 240.  When needed, the conference space can transition into three smaller classrooms by operable partitions.  Other space on the first floor consists of a catering kitchen, student vending area, and indoor lobby with elevators and restrooms. The second and third level consists of classrooms, restrooms, and utility rooms. 

The new building is a steel structure, and exterior materials consist of brick, plaster, glazing. New landscape compliments the existing landscape and creates flow to the building entries while carving out a new destination spot on campus for the students to study and hang out.  The new building mechanical system will be incorporate natural ventilation and in-slab radiant pipe cooling.  This system, along with other sustainable features, will contribute to this being the first Zero Net Energy classroom building in the CSU system as well as earning the prestigious US Green Building Council’s LEED Platinum certification.

  • Project Cost: $31,888,875.00
  • Construction Start Date: February 20, 2017
  • Construction Completion Date: August 23, 2018
  • Project Delivery Method: Collaborative Design-Build
  • Architect: ZGF Architects
  • Design-Builder (Contractor): MATT Construction
  • University Design and Construction Team:
  • Mark Zakhour- Senior Manager, Construction Services
  • Lisa Salgado- Construction Manager
  • Jason Chao- Project Control Specialist
  • Tom Sanchez- Inspector of Record

Photo of CCPE Building

Internal View of CCPE Building

 

 

LBSU Softball and Soccer Clubhouse

The new Soccer and Softball Clubhouse is designed to meet the current and future needs of the Women’s Soccer and Softball Teams.   The proposed 5,760 s.f. project houses Women’s Soccer and Softball Teams’ lockers, showers, team lounges, restrooms, coaches’ offices, mudrooms and taping room.

The building has a construction method new to the CSULB, as it is a modular construction built offsite, delivered in modules and put in place.  The modular building will meet CSULB design standards for building construction and infrastructure requirements, along with meeting the California Energy Code. This method of construction helped save time and money on the construction project.

  • Project Cost: $5,948,365.00
  • Construction Start Date: March 12, 2018
  • Construction Completion Date: October 3, 2018
  • Project Delivery Method: Collaborative Design-Build
  • Architect: Cannon Design
  • Design-Builder (Contractor): CW Driver
  • University Design and Construction Team:
    • Monica Amalfitano - Associate Director, Design and Construction Services
    • Marie Jean Ayoub- Construction Manager
    • Karin Montgomery- Project Engineer
    • Tom Gillenwater- Inspector of Record

LBSU Softball and Soccer Clubhouse Exterior Computer Rendering

LBSU Softball and Soccer Clubhouse Interior Computer Render

 

 

SHS Exam Room Renovation

Student Health Services is an outpatient clinic with Primary Care, Women’s Health, and Sports Medicine facilities available for students.  It is located on campus at the corner of Beach Drive and Merriam Way.  The renovation project consists of tenant improvements that will enhance the efficacy of the programs within the building.  The entrance to the building, exam rooms, clinician spaces, and restrooms will be upgraded to meet the current California Building Code and the American with Disabilities Act. 

The project consists of improvements to the upper level and the lower level as well as the exterior path of travel.  Although the flow of traffic through the building will remain intact, exam rooms, clinician spaces, and restrooms will be upgraded to today’s standards.  Patient flow will enhance with the new programming layout, and physician-patient interaction will be more comfortable with the new space layout.  Calm and relaxing design palettes are intended to provide a serene setting.  In addition, a new walkway ramp at the main entry and renovated restrooms provide ease of access. Overall, the improvements will allow the staff to better serve the students and will enhance the patient experience.

  • Project Cost:  $3.7 million
  • Construction Start Date:  April 9, 2018
  • Anticipated Construction Completion Date:  September 18, 2018
  • Project Delivery Method:  Collaborative Design-Build
  • Architect:  Cannon Design
  • Design-Builder:  C.W. Driver
  • University Design and Construction Team:
    • Stephanie Gutierrez – Project Manager
    • Mark Ratoza – Construction Manager
    • Chris Peterson – Project Engineer
    • Gregg Reams – Inspector of Record

Computer Rendering of the SHS Lobby

Computer rendering of an office space