FA1 2nd Floor Renovation

Complete interior alteration of the 2nd floor that includes shooting studio, digital print lab, darkroom, and photo developing sinks for the Photography Department

  • Total Project Cost: $4.85 Million
  • Construction Start Date:  June 5, 2023
  • Construction Completion Date: March 8, 2024
  • Project Delivery Method: Construction Manager at Risk 
  • Architect: AC Martin
  • Construction Manager: 2H Construction
  • University Design and Construction Team:
    • Ben Wilson  Project Manager
    • Vivek Ghimire, Construction Manager
    • Ben Wilson, Project Engineer
    • Danny Blakley, Inspector of Record