You are here

Up and Coming Projects

Up and Coming Projects

Softball and Soccer Locker Room

New 5,700 locker room for the women’s soccer and softball program, located just north of the Softball Field.  Features of the projects include LED interior and exterior lighting, wifi, drought tolerant landscape, and sustainable storm water run off bioswale.

(Attached is rendering)

Construction start date – mid to late March 2018

Construction completion date – Mid September 2018

Contractor:  CW Driver

Architect: Cannon Design

Estimated Project Cost: $5.7M

USU MEP Upgrades 

Infrastructure upgrades to the USU to include updates to the mechanical air conditioning systems, energy efficient upgrades to the Domestic Hot Water System, Lighting Retrofits to the LED and upgrades to lighting controls, and All Gender restroom installation along with a foot washing station.

Construction start date – Mid May 2018

Construction completion date – Mid November 2018

Contractor:  DPR

Engineer: P2S Engineering

Estimated Project Cost: $2.8M

SHS Exam Room Renovation 

Renovation of existing Exam rooms in Student Health Services, ADA upgrades, and lighting Retrofits to the LED

Construction start date – Mid May 2018

Construction completion date – Mid August 2018

Contractor:  CW Driver

Architect: Cannon Design

Estimated Project Cost: $3.2M

Dance Studio / Lab HVAC Upgrades

Upgrades and added air conditioning and ventilation to the Dance Studio and labs

Construction start date – Mid May 2018

Construction completion date – Mid August 2018

Contractor:  Swinerton

Engineer: P2S Engineering

Estimated Project Cost: $1.4M

Parking Lot 16/G4 Upgrade  

Upgrade to existing parking lot G , ADA upgrades, new exterior LED lighting, wifi, and sustainable storm water run off system.

Construction start date – mid to late March 2018

Construction completion date – Mid September 2018

Contractor:  CW Driver

Architect: Cannon Design

Estimated Project Cost: $3.7M

Library Starbucks Upgrade

Upgrade to existing Library Starbucks

Construction start date – Mid May 2018

Construction completion date – Mid August 2018

Contractor:  2H Construction

Architect / Engineer: AEPC

Estimated Project Cost: $325,000