Student Health Services (SHS) Fire Sprinkler Upgrade
This project will add a fire sprinkler system to the entire Student Health Services Building. This Building Code upgrade will also allow for future tenant improvements to be performed.
- Total Project Cost: $3,401,076
- Construction Start Date: May 22, 2023
- Construction Completion Date: May 5, 2024
- Project Delivery Method: Construction Manager at Risk (CMAR)
- Architect: MMA Architects
- Construction Manager at Risk: 2H Construction
- University Design and Construction Team:
- Stephanie Gutierrez, Project Manager
- Satish Sadhu, Construction Manager
- Dana Morley, Project Engineer
- Tammy Hinds, Inspector of Record