|
news
Campus
begins beauty makeover
By Jo Appleton
Summer On-line Forty-Niner
While Cal State
Long Beach students are off for the summer getting their beauty
rest, ‘there’s no rest for the wicked ones’ who are still
on campus working at getting it beautiful before the start
of the new fall semester.
The Outpost cafeteria located on lower campus, across from
the SSPA Building, is undergoing constructive work to have
new campus awnings installed with wooden trellis’s, so that
plants can be placed around the top perimeter of the building.
The project involves removing old columns, awnings and concrete
around the café and replacing them with 16 new columns,
eight on either side, that will be finished with brick veneer.
A wooden lattice awning will provide a decorative trim around
the top and be lined with planters, said Scott Charmack, associate
vice president of physical planning and facilities management
at CSULB.
The Forty-Niner Shops are funding the project to make the
popular little café more appealing, said Charmack,
who said it’s one of the smaller projects on campus.
But at the cost of $69,284, it may be a small project
but it has a big ticket.
“It sounds simple, but it’s not,” said Sue Brown, director
of physical planning on campus.
The primary reason the cost for the project is so high, Brown
said, is because the columns, originally planned to be attached
to the building, have to be designed in a such a way to be
able to support themselves, a structural detail that drove
costs higher than expected.
The structural engineers for the job did not permit the concrete
columns to be attached to the building, they must be free
standing structures in order to withstand the weight of the
wood trellises, Brown said. In spite of the setback, Charmack
said that The Outpost project will be completed before the
fall semester.
In addition to the Outpost, the SSPA building is also going
under a facelift. Contractors have been working on the building
since July 8 to remodel business offices and classrooms in
the building’s basement. The building has remained open during
construction work but contractors are scheduled to seal off
the basement Friday for the removal of old floor tiles and
asbestos treatment, according to a department memo Tuesday.
There are 40 to 50 other construction jobs going on around
campus, said Charmack. Among the bigger ones is the science
building across from the Student Union, which is making progress
but is still at least two months behind schedule, said Charmack.
There are 70 to 80 trades people working daily on the job,
which was originally scheduled for completion in January 2003,
but Charmack said the contractors now have estimated the completion
time to be sometime in March. The contractor not meeting the
schedule deadlines created the delays, said Charmack.
In other construction business, the Fine Arts buildings, FA1
and FA2 are almost finalized, according to Charmack, and the
department is now occupying them. FA3 and FA4 are still in
progress with final details of health and safety codes, seismic
and fire specifications and disabled students accessability
being completed.
The original scope of the work to be done will not be met
because of funding limitations, said Charmack, but all four
buildings will be back in operation by the start of the fall
semester.
Finally, the telecommunications infrastructure overhaul is
well underway at different locations around campus. The most
apparent one being the open trench on West Campus Drive across
from the library. It’s the underground work for the new 1,800
square foot building being built to house the new voice and
data equipment, according to Charmack.
The building is one of three that will be used as main distribution
points to run copper cable from to feed the voice data signals
around campus. Charmack said fiber optics are typically used
but that it would have been too expensive to wire a campus
as big as CSULB, so the university decided to use copper instead.
The two other buildings being built are to feed cable to other
parts of campus. One is being built within the management
and facilities yard, near the south end of Lot 11, which will
be 1,100 square feet. The third building is the smallest at
700 square feet, and will feed the West side of campus, which
is primarily housing, said Charmack.
The telecommunications infrastructure project is a two-year
project that is only about five months along, but Charmack
said that the plan is to get the underground and exterior
work completed first so that when students return in the fall
semester, major roadways and parking structures will still
be accessible.
|

|
Alisha
Gomez/Summer On-line Forty-Niner
The Outpost cafeteria will have new awnings
installed with wooden trellises.
ADVERTISEMENT
ADVERTISEMENT
Search our site
DEPARTMENT
OF
JOURNALISM
ONLINE 49ER
DEPARTMENTS
ADVERTISING
ADMINISTRATION
DAILY
49ER ALUMNI
SUBSCRIPTION
SERVICE
GIVE
FEEDBACK
|