Online 49er Flag
Online Forty-Niner: Summer Session: News
.

ADVERTISEMENT
Advertisement

.

VOL. VIII, NO. 126
CALIFORNIA STATE UNIVERSITY, LONG BEACH
THURSDAY JULY 5, 2001


ADVERTISEMENT

Advertisement

ADVERTISEMENT

CLASSIFIEDS CLICK HERE

  • Jobs
  • Housing
  • Announcements


POLLS
BULLETIN BOARD
DAILY 49ER E-SHOP



Editorial Staff

Gabriel Lefrancois
Editor in Chief

Michael Watanabe
City Editor

Tanya Dellaca
Photo Editor

Mike Haubrich
Opinion Editor

William Mulligan
Publisher

Gerard Greenidge
Webmaster

news:

Asbestos may halt construction on fountain

By Jamie Rogers
Summer Forty-Niner

Students who attempt to traverse the Brotman Hall plaza this summer are forced to retrace their steps and walk around the building while the area undergoes desperately needed repair.

The plaza, which houses a decorative fountain and is a major facility to many areas of campus, has leaked water into the basement offices below it for years, according to Scott Charmack, associate vice president of physical planning and facilities management at Cal State Long Beach.

"[The area] leaks like a sieve," he said. "We have had hundreds, maybe thousands of feet of gutter trying to take care of the water. We knew we had to replace the deck at some point. It just kept getting worse and worse and worse. To be honest, we put it off because it is  really expensive and a pain to do."

The original price, a $539,503 bid by Anderson White General Contractors, is expected to skyrocket due to an unforeseen asbestos problem. The plaza has three components to it; the walking deck made of concrete, which is visible; a thin waterproofing membrane underneath the walking deck; and a structural deck under the waterproofing layer.

"The waterproofing membrane obviously wasn't doing its job," Charmack said. "We have to get down to the structural deck so we could put down a new waterproofing membrane and then a new concrete walking deck. Where it gets a little sticky is that the membrane had a small amount of asbestos in it."

Asbestos is a strong, fireproof fiber that was used in thousands of products in the 1960s and '70s. If inhaled, the fiber can increase the risk of lung cancer, including a rare type of cancer called mesothelioma, and a lung disease known as asbestosis. When asbestos is discovered on a construction site, strict guidelines must be followed in its removal and disposal.

When the asbestos was discovered in the Brotman Hall plaza, CSULB was forced to dispose of the concrete and the waterproofing membrane as hazardous material, which could cost an estimated $60,000, even though the final bill will reflect a credit from the contractor's original bid on the concrete removal before asbestos was discovered, says Charmack. Along with the added cost of the hauling, CSULB also paid for an independent, third party to monitor air quality in the area.

"People were concerned about the asbestos," Charmack said. "So not only did we have the code-required industrial hygienist on the job, but we paid extra to have [air] sampling [in the offices] down below.

"What we are finding is that the [airborne] asbestos is almost negligible," he continued. "The monitoring was done simply to alleviate people's fears. We never thought asbestos would be picked up and 30 years from now 100 people would die from this job. Never."

Cape Environmental, the company who provided the industrial hygienist to test the air, found an average of .002 particles of asbestos in its latest air sampling on June 20. This amount is well below the permissible exposure limit of .1 particles. The highest amount of asbestos particles, .011 found on June 6,was still well below the acceptable level.

The time it took to test the air and appropriately handle the asbestos-containing material may lead to a delay in completion of the job, according to Charmack.

"There will probably be a couple of days of additional work," he said. "And the campus paid for accelerated work, for double shifts. We [the contractor and the campus] are working together to find a way to get this done."

While admitting that the job is not running on schedule at the moment, Aaron Oedewal, construction manager of Anderson White, said he is confident the job will be finished in a timely manner.

"We will be back on track shortly, he said."We definitely expect to have it done on time."

Charmack said he believes the company intends to meet their contractual obligation, but said he is concerned about the pace of the job. On Tuesday, construction had not taken place for seven days.

"I will be the first to admit that we have had some problems with the contractor, but some abatement should start tonight [Tuesday]," he said.

"We are concerned because they were given the directive to work. It has been a little more difficult now than anyone anticipated but we have to have this deck open before school starts. Can you imagine trying to have school without that deck open?

"In the meantime," Charmack said, "the contractor has to pay liquid damages if they don't get it done on time. They will have to pay a penalty."

filler

Construction

Jamie Rogers/Summer Forty-Niner
Construction outside Brotman Hall is halted when asbestos was discovered in the leaking fountain.


ADVERTISEMENT

Advertisement

ADVERTISEMENT


Search our site




DEPARTMENT OF
JOURNALISM


ONLINE 49ER

DEPARTMENTS

ADVERTISING
ADMINISTRATION
DAILY 49ER ALUMNI
SUBSCRIPTION SERVICE


GIVE FEEDBACK


ADVERTISEMENT

House Ads

ADVERTISEMENT


©2001 Daily Forty-Niner. All rights reserved.