Online Forty-Niner: Fall 2001: NEWS
Online 49er Flag
. ADVERTISEMENT
Advertisement
NEWS | OPINION | DIVERSIONS | SPORTS | CLASSIFIEDS | BACK TO SCHOOL
POLLS | BULLETIN BOARD
| SHOP | CALENDAR | KALEIDOSCOPE 2001 | SURVIVAL GUIDE

LONG BEACH VA HOSPITAL-BLOOD HOTLINE (562) 494-2611 EXT. 2823 RED CROSS - 1-800-GIVE LIFE
.
VOL. IX, NO. 7
CALIFORNIA STATE UNIVERSITY, LONG BEACH
SEPTEMBER 5, 2001


ADVERTISEMENT

Advertisement

ADVERTISEMENT

CLASSIFIEDS CLICK HERE

  • Jobs
  • Housing
  • Announcements


POLLS
BULLETIN BOARD
DAILY 49ER E-SHOP




Editorial Staff

Phil Witte
Editor in Chief

Lyndsey Shinoda
Managing Editor

Michael Watanabe
News Editor

Jamie Rogers
City Editor

Christine Shin
Diversions Editor

Mike Haubrich
Sports Editor

Cara Gavcia
Photo Editor

Chris Burnett
News Editorial Director

Raul Reis
News Operations Director

William Mulligan
Publisher

Gerard Greenidge
Webmaster

news

Brotman facelift near completion

By Dwight Flenniken III
On-line Forty-Niner

Lack of cooperation between employees of Cal State Long Beach and Anderson-White Construction helped fuel major delays in construction at the Brotman Hall plaza this summer.

Aaron Oedewaldt, construction manager for Anderson-White, said he expects the work in front of Brotman Hall to be finished in two weeks.

"We haven't ever gotten a schedule from them," said Dale Hartman, project manager at CSULB after learning of the two-week projection.

Construction on the plaza was originally scheduled for completion prior to the start of the fall semester. The project began the Saturday after commencement took place.

Early in on in the project, asbestos was found in the area. The abatement took a total of 28 days and is one of the reasons Anderson-White gives for pushing back the finish date.

"[Abatement] is a fairly sophisticated process," said Mike Richwine of the California Fire Marshals office.

However, Scott Charmack, director of Physical Planning and Facilities Management, said he does not believe abatement should have stalled the project for this long.

"The reason for the delay has nothing to do with the abatement issue," Charmack said.

Other reasons Anderson-White gives for the lack of progress have less to do with construction problems than they do with CSULB personnel issues. Oedewaldt said their company received no cooperation from campus employees.

"Anderson-White has done everything possible to keep this project moving forward," Oedewaldt said.

Another difference of opinion arose in the exact type of work done by Anderson-White.

"We've done work we haven't got change orders from," Oedewaldt said. "There was a complete change of scope from our contract work. We forced our subs to do work that is up and above their contract with us."

CSULB officials said they do not agree with the Oedewaldt statement.

This is not the first contractual problem Facilities Management has faced. Contractor default managed to push back the finish date on two buildings in the Fine Arts department. What should have been a completed job is now scheduled to conclude in February 2002.

Facilities Management oversees all campus construction projects, construction inspection and project management. Another responsibility is to keep the campus attractive and conducive to student learning, according to their Web site.

As far as the plaza is concerned, Oedewaldt said he believes Anderson-White is completing the project in a timely manner.

The rift between the two agencies lies in the definition each has of exactly how much time is timely.

filler

Construction

Phil Witte/On-line Forty-Niner

Beyond the fences, the almost new and improved Brotman Hall Plaza waits to be unveiled.


ADVERTISEMENT

Advertisement

ADVERTISEMENT


Search our site




DEPARTMENT OF
JOURNALISM


ONLINE 49ER

DEPARTMENTS

ADVERTISING
ADMINISTRATION
DAILY 49ER ALUMNI
SUBSCRIPTION SERVICE


GIVE FEEDBACK


ADVERTISEMENT

House Ads

ADVERTISEMENT


©2001 Daily Forty-Niner. All rights reserved.