Summer road repairs continue
By Maya Yamane
Summer Forty-Niner
Various roads throughout
Cal State Long Beach will be undergoing repair and/or replacement, according
to Michael Kelly, assistant director of Planning and Design Services.
The roads will remain
open during construction. Traffic control personnel will be present
to direct drivers and pedestrians through the construction zone.
According to Kelly,
the start dates, as well as the approximate number of days required to
complete each of the sites, are the contractor’s best-estimate based on
the scope of the work to be completed and may be changed as work progresses.
The campus community will be notified if there is any major change in the
schedule.
The project, coordinated
by Physical Planning and Design Services, is scheduled to begin work on
Monday, July 19 and should be completed in approximately 45 days.
Minor inconveniences
may occur as with any construction project, according to Kelly, due to
some noise and dust generated from demolition operations and odor resulting
from the installation of the new asphalt.
Repair schedule
Where: Earl Warren Drive
When: July 19 (for 30 days)
Where: Atherton Street to State University
Drive along Merriam Way
When: August 5 (for 16 days)
Where: West Campus Turnaround
When: July 23 (for 10 days)
Where: East Campus Drive
When: July 19 (for 17 days)
Where: South Campus Drive
When: August 16 (for 14 days)
Where: Crosswalk in front of Brotman Hall
When: August 5 (for 16 days)
|
|
|