Hall of Science Building Project
Print this pageAdd this page to your favoritesSelect a font sizeSelect a small fontSelect a medium fontSelect a large font
 

Project Schedule

Schedule Update August 2009

  • February 2008 — Project Start
  • April 2008 — Contractor mobilize onsite
  • May - June 2008 — Abatement of hazardous building material / underground utility relocations
  • June - September 2008 — Hard demolition of existing buildings
  • October - December 2008 — Earthwork/Shoring operations
  • January 2009 - March 2009 — Project Suspension due to State Budget Crisis
  • April - July 2009 — Structural concrete and utilities
  • July-October 2009 — Structural Steel
  • October 2009 - January 2010 — Build-out of building exterior
  • January - October 2010 — Interior build-out and finishes
  • October 2009 - January 2010 — Sitework, Landscaping
  • November 2010 - May 2011 — Systems commissioning, complete punch-lists, start-up of equipment
  • May 2011 — Completion