Step | Date(s) |
---|---|
Mobilize/Soft Demo | 7/1/19 |
Demolition | Early August 2019 |
Start Site Preparation | Mid-August 2019 |
Start Foundation | Mid- September 2019 |
Start Vertical Construction (Building) | January 2020 |
Housing Target Completion (Ready for Fall 2021 Semester) | July 2021 |