Land Acquisition CSULB Technology Park application submitted to City of Long Beach Naval Properties Reuse Committee 1992
Land Acquisition CSULB Technology Park proposal ranked first in priority of 12 proposed reuses for the Cabrillo Naval Housing Site by the City of Long Beach Naval Properties Reuse Committee and City Council 1992
Land Acquisition CSULB Foundation submitted an application to the U.S. Navy for an Economic Development Conveyance June, 1995
Land Acquisition CSULB receives title to the property via the Navy's first Economic Development Conveyance nationwide July, 1996
Project Funding CSULB receives initial grant funding from U.S. Department of Commerce, Economic Development Administration and California Trade & Commerce Agency 1997
Ground breaking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . April, 1998
Phase I Demolition / Renovation Commences October, 1997
Phase I Demolition Complete 8 acres of Finished Lots Available August, 1998
Phase II Demolition Complete 4 Additional Acres of Finished Lots Available April, 1999
Tenant Occupancy Initial Tenants, the Alameda Corridor Training Project and the Long Beach Enterprise Center take occupancy of existing buildings renovated into offices Spring / Summer, 1999
Phase III Demolition Complete, final 8 Acres of Finished Lots March, 2000
Phase III Final Infrastructure, landscape improvements (completion of all site work) Fall, 2000
Private Industry Buildings Initial phase of buildings started: completed Spring/ Summer 2001