| Phase | Description | Date |
|---|---|---|
| Land Acquisition | CSULB Technology Park application submitted to City of Long Beach Naval Properties Reuse Committee | 1992 |
| Land Acquisition | CSULB Technology Park proposal ranked first in priority of 12 proposed reuses for the Cabrillo Naval Housing Site by the City of Long Beach Naval Properties Reuse Committee and City Council | 1992 |
| Land Acquisition | CSULB Foundation submitted an application to the U.S. Navy for an Economic Development Conveyance | June, 1995 |
| Land Acquisition | CSULB receives title to the property via the Navy's first Economic Development Conveyance nationwide | July, 1996 |
| Project Funding | CSULB receives initial grant funding from U.S. Department of Commerce, Economic Development Administration and California Trade & Commerce Agency | 1997 |
| Ground breaking | . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . | April, 1998 |
| Phase I | Demolition / Renovation Commences | October, 1997 |
| Phase I | Demolition Complete 8 acres of Finished Lots Available | August, 1998 |
| Phase II | Demolition Complete 4 Additional Acres of Finished Lots Available | April, 1999 |
| Tenant Occupancy | Initial Tenants, the Alameda Corridor Training Project and the Long Beach Enterprise Center take occupancy of existing buildings renovated into offices | Spring / Summer, 1999 |
| Phase III | Demolition Complete, final 8 Acres of Finished Lots | March, 2000 |
| Phase III | Final Infrastructure, landscape improvements (completion of all site work) | Fall, 2000 |
| Private Industry Buildings | Initial phase of buildings started: completed | Spring/ Summer 2001 |